Chris Walterson
 

I've given myself a bit of time to think of the ailerons, so in the meantime I started on the elevators.

 I have some of the original plans [Q2] . The ones with the U joint in the torque tube. I have read most of the newsletters and I think

I have it figured out, but i want to pass it by others that have gone before.

I have the center stick and a passenger stick. I have all the control tubes installed to the elevator bellcranks.

  I will set both elevators at 15 degrees trailing edge up,  as in the rigging template, and lock them in place.

I will then push my control sticks as far forward as possible. Mount the mass balance about 1/8 inch from top of canard.

 Drill 1/8 hole in bellcranks  and mass balance and install pop rivet to stabalize.   Drill 3/16 holes and install AN3 bolts.

 I may see how much down travel I have before I drill the AN3. The rivets will hold temporarily.

 Makes sense????                Take care--------------  Chris


--
This email has been checked for viruses by Avast antivirus software.
https://www.avast.com/antivirus


Mike Steinsland
 

That's what I did
Keep in mind when you deflect the stick left or right for ailerons the coresponding elevator will deflect a bit

On Sun., May 2, 2021, 8:36 p.m. Dorothea Keats, <dkeats@...> wrote:
  I've given myself a bit of time to think of the ailerons, so in the
meantime I started on the elevators.

  I have some of the original plans [Q2] . The ones with the U joint in
the torque tube. I have read most of the newsletters and I think

I have it figured out, but i want to pass it by others that have gone
before.

I have the center stick and a passenger stick. I have all the control
tubes installed to the elevator bellcranks.

   I will set both elevators at 15 degrees trailing edge up,  as in the
rigging template, and lock them in place.

I will then push my control sticks as far forward as possible. Mount the
mass balance about 1/8 inch from top of canard.

  Drill 1/8 hole in bellcranks  and mass balance and install pop rivet
to stabalize.   Drill 3/16 holes and install AN3 bolts.

  I may see how much down travel I have before I drill the AN3. The
rivets will hold temporarily.

  Makes sense????                Take care--------------  Chris


--